Extension of time claims submitted to USACE, Port Authority, state DOTs, and other public authorities are rejected more often than they should be — not because the delay did not happen, but because the claim package does not meet the internal standard of proof that the agency reviewer applies.

Understanding that standard before you prepare the claim is the difference between a negotiated settlement and a protracted dispute.

What Public Agencies Are Actually Evaluating

When a public agency reviewer receives an EOT claim, they are working through a sequence of questions. Did the delay actually occur? Was it caused by the owner or a compensable force majeure event? Did it affect the critical path at the time it occurred? Was the contractor diligent in mitigating the impact? And does the schedule analysis demonstrate all of the above using methodology consistent with the contract?

A claim that cannot answer all five of these questions with contemporaneous documentation will not be approved — regardless of how large the delay was or how clearly the contractor was impacted.

The Schedule Analysis

Most public agency scheduling specifications require TIA methodology for delay quantification. The TIA must be based on the accepted schedule update in effect at the time the delay event occurred — not the original baseline. It must insert the specific delay event with appropriate duration and logic, and demonstrate the resulting push to the critical path and project completion.

Common mistakes: using the baseline instead of the contemporaneous update, inserting the delay as a constraint rather than an activity, failing to address float consumption before the critical path was impacted, and not addressing concurrent contractor-caused delays.

The Entitlement Documentation

The schedule analysis answers how long the delay was. The entitlement documentation answers why the owner is responsible for it. This requires the contract clause that creates the entitlement, the specific event or action that triggered it, the date it occurred, and the notice provided to the owner. Missing any of these elements gives the reviewer grounds to deny entitlement regardless of the schedule analysis.

Formatting for Agency Review

Public agency reviewers process many claims. A claim that is clearly organized — executive summary, entitlement basis, schedule analysis, supporting documentation — gets a fair review. A claim that buries the critical path analysis in 200 pages of attachments without a clear narrative creates work for the reviewer and reduces the likelihood of approval.

Structure the claim the way you would structure a report for someone who is skeptical and time-constrained, because that is exactly who is reading it.