Quick answer: Time Impact Analysis fits projects with a sound baseline and discrete, documentable delay events; Windows Analysis fits complex projects with multiple concurrent delays and a complete series of contemporaneous updates; Collapsed As-Built fits completed projects where a reliable periodic update record was never maintained.

Three Methods, One Decision

Time Impact Analysis (TIA), Windows Analysis, and Collapsed As-Built are three of the forensic delay methodologies most frequently used on construction delay claims. Each has already been compared head-to-head elsewhere on this site — see TIA vs. as-built: choosing a delay method and windows analysis vs. collapsed as-built for the two-way breakdowns. This guide puts all three side by side, because the real-world decision is rarely a straight choice between two options — it is an assessment of which single method, among several, actually fits the record a specific project produced.

Side-by-Side Comparison

FactorTime Impact Analysis (TIA)Windows AnalysisCollapsed As-Built
How it worksInserts a specific delay event into the accepted baseline (or latest update) at the point in time it occurred, and measures the push to the completion date.Divides the project timeline into discrete windows, usually bounded by schedule updates, and analyzes how the critical path changed within each window.Starts from the as-built schedule and removes specific delay events one at a time to show what completion would have been without them.
Records requiredA well-developed baseline schedule with honest logic and float, and discrete, documentable delay events.A complete, logically sound series of contemporaneous CPM updates covering the disputed period.A detailed as-built schedule (often reconstructed from daily reports, RFIs, submittals, and correspondence) and a documented basis for each delay event removed.
Best suited forContracts where the specification requires TIA, and where delay events can be analyzed close to when they occurred.Complex projects with multiple, possibly concurrent, delays from more than one party.Completed projects where contemporaneous updates are missing, inconsistent, or were never maintained.
StrengthsMost widely specified and accepted by public agencies; analyzes delay close to the time it occurred.Most rigorous for isolating concurrent delay and assigning responsibility between parties; anchored to documents that existed before the dispute.Usable even when no reliable update history exists; works from what actually happened rather than a theoretical projection.
WeaknessesLoses credibility if the baseline was poorly built or float was artificially constrained.Time- and record-intensive; not usable without a reasonably complete update series.More vulnerable to challenge because it depends on assumptions about what would have happened absent the delay, developed after the fact.

How to Choose Among the Three

  1. Check the contract's scheduling specification first. If TIA is specified, use TIA — deviating from a specified method invites an immediate challenge regardless of the analysis quality.
  2. Inventory the schedule update history. A complete, logically sound series of contemporaneous updates supports Windows Analysis. A thin or inconsistent update history pushes the choice toward Collapsed As-Built or, where only the original baseline survives, Impacted As-Planned.
  3. Assess whether delays are discrete or concurrent. A small number of clearly separable delay events fits TIA well. Multiple delays from different parties overlapping in time are better isolated through Windows Analysis.
  4. Confirm the project status. An active project with ongoing updates supports TIA or Windows Analysis performed in near-real time. A completed project being analyzed after the fact, with no usable update series, is the typical Collapsed As-Built scenario.
  5. Apply the method consistently. Switching methods mid-analysis because a different one produces a more favorable number is one of the fastest ways to lose credibility with a reviewer or opposing expert.

The Underlying Requirement Is the Same

Regardless of which of the three methods applies, the common requirement is a schedule and field-record history thorough enough to support the analysis honestly. Methodology selection optimizes what is possible with the record a project actually produced — it cannot substitute for a record that was never created. That is the case for building and maintaining schedules defensibly from the baseline forward, discussed further in forensic delay analysis and extension of time claims.