CPM Scheduling for VA Construction Projects in New York

VA medical centers and clinics across New York renovate and expand while continuing to treat patients. This page explains how HADVEN's CPM scheduling � informed by a documented VA facility-renovation project elsewhere in the federal system � applies to that kind of work.

Documented VA Scheduling Experience

HADVEN has documented VA scheduling experience: a Primavera P6 CPM baseline for the renovation of Buildings 309A and 309B at the Martinsburg, WV VA Medical Center, built to VA Section 01 32 16.15. That project demonstrates familiarity with VA scheduling specifications and review cycles � this page describes how that capability applies to VA facility work in New York.

What VA facility work in New York looks like

VA hospital and medical center construction in New York covers new facility construction, major renovation, and building-system replacement, almost always performed while the facility continues treating patients.

  • VA hospital and medical center construction
  • Medical facility renovation and modernization
  • Healthcare infrastructure and building-system upgrades
  • Phased construction in occupied clinical space

What makes VA healthcare work harder to schedule

Infection control and interim life safety requirements, utility outage coordination, and a formal VA review-and-acceptance cycle for every plan and shop drawing all shape the schedule logic before a single activity gets built. The Martinsburg project carried exactly this structure � the same approach applies to a New York VA facility.

  • Phased construction in occupied healthcare facilities
  • ICRA and Interim Life Safety Measure (ILSM) coordination
  • Utility outage requests (steam, electrical, fire alarm, domestic water)
  • Federal construction scheduling specifications and VA review cycles

Services and deliverables

A VA baseline needs a formal review-and-acceptance cycle built into the logic for every submittal, not tracked as a side process. HADVEN's documented VA project carried this exact structure � the same scheduling approach applies to VA facility work in New York.

  • CPM baseline schedules built to VA scheduling specifications
  • VA review-and-acceptance cycle logic for submittals and shop drawings
  • Long-lead procurement tracking
  • Monthly updates with a written progress narrative
  • Time Impact Analysis and Extension of Time support

Common questions

What VA scheduling experience does HADVEN have?

HADVEN has a documented CPM baseline schedule for the renovation of Buildings 309A and 309B at the Martinsburg, WV VA Medical Center, built to VA Section 01 32 16.15, demonstrating familiarity with VA scheduling specifications and review cycles.

What kind of VA projects does this apply to?

VA hospital construction, medical facility renovation, and healthcare infrastructure upgrades performed in occupied healthcare facilities, including New York VA medical centers.

What does HADVEN's documented VA project include?

A Primavera P6 baseline schedule for a 359-calendar-day VA renovation contract, covering hazardous materials abatement, building-by-building sequencing, discipline-specific shop drawing review, and the VA review-and-acceptance cycle. See the VA Medical Center Renovation case study.

Have a VA facility project in New York?

Send the contract scheduling specification and HADVEN will outline how the baseline should be structured.