VA 613-26-104 � Renovation of VA Medical Center, Buildings 309A and 309B
A Primavera P6 CPM baseline built to the VA scheduling specification for a 359-calendar-day federal healthcare renovation, sequenced building-by-building through substantial and final completion.
What the baseline schedule covers
The project renovates two single-story buildings at the Martinsburg VA Medical Center into open-plan offices. The work runs as a single phase, with each trade finishing in Building 309A before moving on to Building 309B. The schedule is built to the VA scheduling specification (Section 01 32 16.15) and carries hazardous materials abatement, selective demolition, crawl space and roof truss repairs, a new standing seam metal roof, windows and storefronts, exterior porches and canopy, and new mechanical, plumbing, fire protection, electrical and low-voltage systems through to substantial and final completion.
Submittals, long-lead procurement, VA review periods and inspections, testing and balancing, and commissioning are tied into the schedule logic rather than tracked separately, so the baseline reflects how the project is actually expected to be built and reviewed.
This summary is based on the baseline schedule (Rev.00) HADVEN prepared for the project. Contract value and project outcome are not published here.
The scope evidenced in the schedule
- Preconstruction and mobilization, including steam, domestic water, electrical and fire-alarm outage requests coordinated with VA utility shutdowns.
- General submittals carried through a formal VA Review & Acceptance cycle for every plan � Accident Prevention Plan, Quality Control Plan, Submittal Register, Waste Management Plan, ICRA & ILSM Plan, Lead Compliance Program, Environmental Protection Plan, and the Baseline CPM Schedule itself.
- Shop drawings organized by discipline � Structural, Architectural, Mechanical/HVAC & Controls, Plumbing, Fire Protection, Electrical, and Communications/Fire Alarm/Security � each with its own Prepare & Submit and VA Review & Approval cycle.
- Environmental and hazardous materials work, including the asbestos abatement plan and lead paint removal plan.
- Long-lead procurement tracking for the aluminum canopy, tubular daylighting devices, metal roofing, exterior windows and storefronts, mechanical equipment, electrical/communications/security equipment, doors/finishes/casework, structural steel, and plumbing and fire protection materials.
- Building-by-building construction sequencing: hazardous materials abatement in Building 309A is completed before abatement begins in Building 309B, with the same trade-by-trade sequence carried through to substantial and final completion.