Westchester Athletic Upgrades � LAUSD

A Primavera P6 schedule update tracking phased softball, baseball and football/track field upgrades against the accepted baseline for Los Angeles Unified School District.

LOCATIONLos Angeles, CA
SECTORK-12 public school construction
HADVEN SERVICECPM Schedule Updates & Progress Monitoring

What the schedule update shows

ProjectWestchester Athletic Upgrades
OwnerLos Angeles Unified School District (LAUSD)
Project TypeK-12 athletic facility upgrades
Schedule Duration259 working days
Sample TypeSchedule update (progress after baseline acceptance)
Service EvidencedCPM Schedule Updates & Progress Monitoring � Primavera P6

This sample is a schedule update, not a baseline. It records actual start and finish dates and percent complete against the accepted baseline, with the remaining work re-forecast to completion. The project upgrades three athletic facilities in phases: Phase 1A softball field, Phase 1B baseball field, and Phase 1C football field and track.

The schedule tracks submittals and owner review by facility, long-lead procurement such as scoreboards, bleachers and storm-trap (Contech) systems, demolition, grading, underground electrical and drainage, field construction, and contract milestones through substantial and final completion � including an owner shutdown/school-events window and a rain-day allowance carried directly in the logic.

This summary is based on the schedule update HADVEN prepared for the project. Contract value and project outcome are not published here.

The scope evidenced in the schedule

  • Three parallel work streams � softball, baseball, and track & field � each with its own submittal, owner review, procurement and construction sequence.
  • Long-lead procurement tracking for scoreboards, bleachers, dugout systems, and storm-trap (Contech) systems by field.
  • Demolition, grading, underground electrical and drainage, and field construction sequenced by facility and phase.
  • Shared sitewide scope � perimeter fencing, underground electrical, site drainage, irrigation and sod, and paving � coordinated across all three phases.
  • An owner shutdown/school-events window and a rain-day allowance built into the update logic, consistent with an operating school campus.
  • Progress recorded against the accepted baseline: actual start/finish dates, percent complete, and re-forecast remaining duration.
Schedule record: Westchester Athletic Upgrades � Primavera P6 schedule update, 259 working days

How the project is phased

Notice to Proceed27-Jul-2026 (actual)
Project start
Critical shop drawings & submittals complete25-Oct-2026
Milestone #2
Completion of mobilization17-Oct-2026
Milestone #3
Baseline complete14-Oct-2026
Milestone #4
Phase 1A complete � softball17-Apr-2027
Milestone #5
Phase 1B complete � baseball17-Apr-2027
Milestone #6
Phase 1C complete � football & track20-May-2027
Milestone #7
Substantial Completion~22-Jun-2027
Punchlist, warranties and closeout follow
Final Completion~22-Jul-2027
259 working days from NTP