Westchester Athletic Upgrades � LAUSD
A Primavera P6 schedule update tracking phased softball, baseball and football/track field upgrades against the accepted baseline for Los Angeles Unified School District.
What the schedule update shows
This sample is a schedule update, not a baseline. It records actual start and finish dates and percent complete against the accepted baseline, with the remaining work re-forecast to completion. The project upgrades three athletic facilities in phases: Phase 1A softball field, Phase 1B baseball field, and Phase 1C football field and track.
The schedule tracks submittals and owner review by facility, long-lead procurement such as scoreboards, bleachers and storm-trap (Contech) systems, demolition, grading, underground electrical and drainage, field construction, and contract milestones through substantial and final completion � including an owner shutdown/school-events window and a rain-day allowance carried directly in the logic.
This summary is based on the schedule update HADVEN prepared for the project. Contract value and project outcome are not published here.
The scope evidenced in the schedule
- Three parallel work streams � softball, baseball, and track & field � each with its own submittal, owner review, procurement and construction sequence.
- Long-lead procurement tracking for scoreboards, bleachers, dugout systems, and storm-trap (Contech) systems by field.
- Demolition, grading, underground electrical and drainage, and field construction sequenced by facility and phase.
- Shared sitewide scope � perimeter fencing, underground electrical, site drainage, irrigation and sod, and paving � coordinated across all three phases.
- An owner shutdown/school-events window and a rain-day allowance built into the update logic, consistent with an operating school campus.
- Progress recorded against the accepted baseline: actual start/finish dates, percent complete, and re-forecast remaining duration.