Documented CPM Case Study
Cherry Hills Facility Improvements Phase I
A facility-improvement baseline coordinating material submittals, approvals, fabrication, demolition, new construction, MEP and closeout.

Selected view of the HADVEN baseline schedule
Project Overview
What the documented schedule shows
ProjectCherry Hills Facility Improvements Phase I
Client / AgencyCity of Menifee
Project TypeMunicipal facility improvements
Schedule Period15-Jun-2026 to 21-Dec-2026
Schedule Duration130 working days
Service EvidencedCPM Baseline Scheduling
The strongest project-controls signal is the integration of procurement-facing material activities with the downstream construction sequence, reducing the schedule to an executable delivery plan rather than a high-level milestone list.
About this case study
This summary is based on the baseline schedule HADVEN prepared for the project. Contract value, final outcome and commercial details are not published here.
Project Controls Scope
The scope evidenced in the schedule
- CPM baseline schedule development evidenced by the detailed baseline schedule.
- Material submittal, review and approval sequencing across electrical, painting, concrete, flooring, framing, drywall, plumbing, HVAC, acoustic ceilings, doors, countertops and cabinets.
- Fabrication and delivery sequencing tied to the construction work plan.
- Construction sequencing covering mobilization, demolition, structure, architecture, plumbing, electrical, HVAC, trash enclosure and closeout.
Schedule record: Cherry Hills Facility Improvements Phase I - Baseline Schedule · 15-Jun-2026 to 21-Dec-2026
Timeline
How the baseline is organized
Baseline / key dates15-Jun-2026 to 21-Dec-2026
130 working daysPrepare & submit15-Jun-2026 to 06-Jul-2026
Material submittalsReview & approve18-Jun-2026 to 03-Aug-2026
Material review workflowConstruction15-Jun-2026 to 24-Nov-2026
Demolition and new constructionCloseout25-Nov-2026 to 21-Dec-2026
Final inspection, punch list, cleaning and demobilizationSchedule Evidence
Selected baseline schedule view
An excerpt of the baseline schedule itself, shown so the sequencing can be reviewed directly.