Construction project controls consultancy
+1 323-305-5054projects@hadven.com

Cherry Hills Facility Improvements Phase I

A facility-improvement baseline coordinating material submittals, approvals, fabrication, demolition, new construction, MEP and closeout.

LOCATIONMenifee, CA
SECTORPublic works / municipal facilities
HADVEN SERVICECPM Baseline Scheduling
Detailed CPM baseline schedule for Cherry Hills Facility Improvements Phase I
Selected view of the HADVEN baseline schedule

What the documented schedule shows

ProjectCherry Hills Facility Improvements Phase I
Client / AgencyCity of Menifee
Project TypeMunicipal facility improvements
Schedule Period15-Jun-2026 to 21-Dec-2026
Schedule Duration130 working days
Service EvidencedCPM Baseline Scheduling

The strongest project-controls signal is the integration of procurement-facing material activities with the downstream construction sequence, reducing the schedule to an executable delivery plan rather than a high-level milestone list.

This summary is based on the baseline schedule HADVEN prepared for the project. Contract value, final outcome and commercial details are not published here.

The scope evidenced in the schedule

  • CPM baseline schedule development evidenced by the detailed baseline schedule.
  • Material submittal, review and approval sequencing across electrical, painting, concrete, flooring, framing, drywall, plumbing, HVAC, acoustic ceilings, doors, countertops and cabinets.
  • Fabrication and delivery sequencing tied to the construction work plan.
  • Construction sequencing covering mobilization, demolition, structure, architecture, plumbing, electrical, HVAC, trash enclosure and closeout.
Schedule record: Cherry Hills Facility Improvements Phase I - Baseline Schedule · 15-Jun-2026 to 21-Dec-2026

How the baseline is organized

Baseline / key dates15-Jun-2026 to 21-Dec-2026
130 working days
Prepare & submit15-Jun-2026 to 06-Jul-2026
Material submittals
Review & approve18-Jun-2026 to 03-Aug-2026
Material review workflow
Construction15-Jun-2026 to 24-Nov-2026
Demolition and new construction
Closeout25-Nov-2026 to 21-Dec-2026
Final inspection, punch list, cleaning and demobilization

Selected baseline schedule view

An excerpt of the baseline schedule itself, shown so the sequencing can be reviewed directly.

Schedule layout showing activities, dates and sequencing for Cherry Hills Facility Improvements Phase I
Selected page from the HADVEN baseline schedule.