Cherry Hills Facility Improvements Phase I

A facility-improvement baseline coordinating material submittals, approvals, fabrication, demolition, new construction, MEP and closeout.

LOCATIONMenifee, CA
SECTORPublic works / municipal facilities
HADVEN SERVICECPM Baseline Scheduling
Detailed CPM baseline schedule for Cherry Hills Facility Improvements Phase I
Selected schedule view from the supplied HADVEN project-control document

What the documented schedule shows

ProjectCherry Hills Facility Improvements Phase I
Client / AgencyCity of Menifee
Project TypeMunicipal facility improvements
Schedule Period15-Jun-2026 to 21-Dec-2026
Schedule Duration130 working days
Service EvidencedCPM Baseline Scheduling

The strongest project-controls signal is the integration of procurement-facing material activities with the downstream construction sequence, reducing the schedule to an executable delivery plan rather than a high-level milestone list.

This case study is intentionally limited to information supported by the supplied schedule and the existing HADVEN project portfolio. The document does not establish a commercial challenge, final outcome, project value, or additional credentials, so those items are not claimed here.

The scope evidenced in the schedule

  • CPM baseline schedule development evidenced by the detailed baseline schedule.
  • Material submittal, review and approval sequencing across electrical, painting, concrete, flooring, framing, drywall, plumbing, HVAC, acoustic ceilings, doors, countertops and cabinets.
  • Fabrication and delivery sequencing tied to the construction work plan.
  • Construction sequencing covering mobilization, demolition, structure, architecture, plumbing, electrical, HVAC, trash enclosure and closeout.
Schedule record: Cherry Hills Facility Improvements Phase I - Baseline Schedule · 15-Jun-2026 to 21-Dec-2026

How the baseline is organized

Baseline / key dates15-Jun-2026 to 21-Dec-2026
130 working days
Prepare & submit15-Jun-2026 to 06-Jul-2026
Material submittals
Review & approve18-Jun-2026 to 03-Aug-2026
Material review workflow
Construction15-Jun-2026 to 24-Nov-2026
Demolition and new construction
Closeout25-Nov-2026 to 21-Dec-2026
Final inspection, punch list, cleaning and demobilization

Selected baseline schedule view

The original supplied schedule is preserved as a portfolio evidence artifact; the website adds context rather than replacing the underlying document.

Schedule layout showing activities, dates and sequencing for Cherry Hills Facility Improvements Phase I
Selected page from the supplied baseline schedule. Client and project details are shown only to the extent contained in the source material provided for this portfolio.