Well 232 Drilling and Testing (1567W)

A drilling and testing baseline that sequences permitting, pilot-hole investigation, aquifer evaluation, well construction, testing and site restoration.

LOCATIONWestern Riverside County, CA
SECTORWater & utilities
HADVEN SERVICECPM Baseline Scheduling
Detailed CPM baseline schedule for Well 232 Drilling and Testing (1567W)
Selected view of the HADVEN baseline schedule

What the documented schedule shows

ProjectWell 232 Drilling and Testing (1567W)
Client / AgencyEastern Municipal Water District
Project TypeWater supply / well development
Schedule Period13-Apr-2026 to 31-Dec-2026
Schedule Duration184 days
Service EvidencedCPM Baseline Scheduling

This is a strong example of sequencing specialized technical work: the schedule nests investigative activities, zone reviews, well construction and multiple testing stages into a single baseline with the project finish held at 31-Dec-2026.

This summary is based on the baseline schedule HADVEN prepared for the project. Contract value, final outcome and commercial details are not published here.

The scope evidenced in the schedule

  • Baseline schedule covering award, NTP, pre-construction and project management/mobilization.
  • Sequencing for a 600-foot pilot borehole, downhole geophysical surveys and four isolated aquifer-zone investigations with district/engineer review.
  • Well construction activities including reaming to 32 inches, caliper survey, bottom seal, casing, gravel pack and well development.
  • Testing, commissioning and closeout including discharge testing, flowmeter survey, video, alignment tests, disinfection/capping and site restoration.
Schedule record: Baseline Schedule - Well 232 Drilling & Testing (1567W) · 13-Apr-2026 to 31-Dec-2026

How the baseline is organized

Award / NTP13-Apr-2026 / 03-Aug-2026
Key contractual milestones
Pre-construction25-Jun-2026 to 24-Jul-2026
Environmental health permit and drilling-fluid program
Pilot drilling & investigation04-Sep-2026 to 15-Oct-2026
600-ft pilot borehole, geophysics and aquifer zones
Well construction16-Oct-2026 to 04-Nov-2026
Borehole, casing, gravel pack and development
Testing & closeout05-Nov-2026 to 31-Dec-2026
Discharge testing, final testing and site restoration

Selected baseline schedule view

An excerpt of the baseline schedule itself, shown so the sequencing can be reviewed directly.

Schedule layout showing activities, dates and sequencing for Well 232 Drilling and Testing (1567W)
Selected page from the HADVEN baseline schedule.