HADVEN LLC
Request a Quote

8th and Roosevelt Active Transportation Corridor

A detailed baseline schedule organizing pre-construction, approvals, procurement, and corridor construction activities for an active transportation program.

LOCATIONNational City, CA
SECTORTransportation & infrastructure
HADVEN SERVICECPM Baseline Scheduling
Detailed CPM baseline schedule for 8th and Roosevelt Active Transportation Corridor
Selected schedule view from the supplied HADVEN project-control document

What the documented schedule shows

Project8th and Roosevelt Active Transportation Corridor
Client / AgencyCity of National City
Project TypeActive transportation / public infrastructure
Schedule Period03-Aug-2026 to 16-Aug-2027
Schedule Duration260 working days
Service EvidencedCPM Baseline Scheduling

The document is particularly useful as proof of sequencing discipline: approvals, procurement, utility coordination, traffic control, demolition and construction are represented as a connected baseline rather than as a simple list of tasks.

This case study is intentionally limited to information supported by the supplied schedule and the existing HADVEN project portfolio. The document does not establish a commercial challenge, final outcome, project value, or additional credentials, so those items are not claimed here.

The scope evidenced in the schedule

  • CPM baseline schedule development evidenced by the submitted schedule package.
  • Pre-construction submittal and review sequences for SWPP, traffic control, demolition, prestressed concrete, traffic signal modifications, and irrigation mainline work.
  • Shop drawing preparation and review for pipe, structural steel, signals and signs, detectors, and general shop drawings.
  • Procurement, fabrication and delivery sequencing followed by construction activities, including utility relocations, traffic control, demolition, and corridor work.
Schedule record: 8th And Roosevelt Active Transporation Corridor - Baseline Schedule · 03-Aug-2026 to 16-Aug-2027

How the baseline is organized

Baseline / key dates03-Aug-2026 to 16-Aug-2027
260 working days
Pre-construction03-Aug-2026 to 11-Sep-2026
Submittal, review and approval workflow
Procurement14-Sep-2026 to 01-Oct-2026
Fabrication and delivery of key materials
Construction10-Aug-2026 to 30-Jun-2027
Mobilization, BMPs, traffic control and corridor work

Selected baseline schedule view

The original supplied schedule is preserved as a portfolio evidence artifact; the website adds context rather than replacing the underlying document.

Schedule layout showing activities, dates and sequencing for 8th and Roosevelt Active Transportation Corridor
Selected page from the supplied baseline schedule. Client and project details are shown only to the extent contained in the source material provided for this portfolio.