Reseda Charter High School � Track & Field Replacement

A Primavera P6 schedule update tracking a phased track-and-field replacement against an LAUSD-accepted baseline, with long-lead procurement and summer-window phasing built into the logic.

LOCATIONLos Angeles, CA
SECTORK-12 public school facilities
HADVEN SERVICECPM Schedule Updates & Progress Monitoring

What the documented schedule shows

ProjectReseda Charter High School - Track & Field Replacement
Client / AgencyLos Angeles Unified School District (LAUSD)
Project TypeK-12 public school athletic facility replacement
Schedule TypeSchedule Update No. 01, data date 31-Oct-2026 � Primavera P6
PhasingPhase 1 (field, track & hardscapes); Phase 2A/2B (summer 2027 work window)
Service EvidencedCPM Schedule Updates & Progress Monitoring

This sample is Schedule Update No. 01, not a baseline. It records actual start and finish dates and percent complete against the accepted baseline, with the remaining work re-forecast to completion. The project replaces the track and field at Reseda Charter High School. Phase 1 covers the field, track and hardscapes, while Phase 2A and 2B work is scheduled for the summer 2027 construction window � a phasing approach common on occupied K-12 campuses, where disruptive work is concentrated into the window school is out of session.

This summary is based on the schedule update HADVEN prepared for the project. Contract value, final outcome and commercial details are not published here.

The scope evidenced in the schedule

  • Schedule update workflow: actual dates, percent complete, and remaining-duration re-forecast against the LAUSD-accepted baseline.
  • Submittals and owner review tracked by scope area, consistent with LAUSD's baseline-review and resubmittal process.
  • Long-lead procurement tracking for the scoreboard, wetland modular system, and storm drain materials.
  • Demolition and removal of existing irrigation piping, field over-excavation and grading, underground electrical, curbs and slot drains.
  • Drainage, irrigation and sod installation, and track paving/surfacing sequenced through substantial and final completion.
  • Phased construction aligned to the academic calendar: disruptive Phase 2A/2B work concentrated into the summer 2027 window.
Schedule record: Reseda Charter High School - Track & Field Replacement � Schedule Update No. 01, data date 31-Oct-2026

How the update is organized

Schedule update data date31-Oct-2026
Schedule Update No. 01, Primavera P6
Phase 1Field, track & hardscapes
Demolition, grading, underground electrical, drainage, irrigation, sod, track paving/surfacing
Phase 2A / 2BSummer 2027 work window
Scoped to the academic-calendar construction window
CloseoutSubstantial and final completion
Tracked against the LAUSD-accepted baseline