Reseda Charter High School � Track & Field Replacement
A Primavera P6 schedule update tracking a phased track-and-field replacement against an LAUSD-accepted baseline, with long-lead procurement and summer-window phasing built into the logic.
What the documented schedule shows
This sample is Schedule Update No. 01, not a baseline. It records actual start and finish dates and percent complete against the accepted baseline, with the remaining work re-forecast to completion. The project replaces the track and field at Reseda Charter High School. Phase 1 covers the field, track and hardscapes, while Phase 2A and 2B work is scheduled for the summer 2027 construction window � a phasing approach common on occupied K-12 campuses, where disruptive work is concentrated into the window school is out of session.
This summary is based on the schedule update HADVEN prepared for the project. Contract value, final outcome and commercial details are not published here.
The scope evidenced in the schedule
- Schedule update workflow: actual dates, percent complete, and remaining-duration re-forecast against the LAUSD-accepted baseline.
- Submittals and owner review tracked by scope area, consistent with LAUSD's baseline-review and resubmittal process.
- Long-lead procurement tracking for the scoreboard, wetland modular system, and storm drain materials.
- Demolition and removal of existing irrigation piping, field over-excavation and grading, underground electrical, curbs and slot drains.
- Drainage, irrigation and sod installation, and track paving/surfacing sequenced through substantial and final completion.
- Phased construction aligned to the academic calendar: disruptive Phase 2A/2B work concentrated into the summer 2027 window.