A contractor working in New York can be scheduling to a federal specification on one project and a state or local agency's own specification on the next � and the two are not interchangeable. Federal work governed by VA or GSA requirements follows a different review structure than state and local New York agencies like OGS, DASNY, NYC DEP, MTA, or the Port Authority. Knowing which framework applies, and what each one actually checks, is the first thing a scheduler should confirm on any given contract.
Federal specifications: standardized, UFGS-rooted language
Federal construction scheduling specifications � including VA and GSA contracts � are typically built around standardized specification language (UFGS-pattern network-analysis-schedule sections), with a formal submittal review cycle built into the contract. HADVEN's documented federal scheduling experience reflects this structure directly: the VA 613-26-104 Medical Center renovation baseline was built to the VA's own scheduling specification (Section 01 32 16.15), with a formal VA Review & Acceptance cycle built into the CPM logic for every submittal � general conditions plans, shop drawings by discipline, hazardous materials plans, and the baseline schedule itself.
What this means in practice:
- Specification language is relatively standardized across federal agencies, even though specific numbering and content vary by contract and by agency (VA vs. GSA vs. USACE).
- Submittal review cycles are formal and typically run on fixed review windows (commonly 10 to 20 calendar days per submittal in HADVEN's documented experience), and schedule logic should reflect that review time explicitly rather than assuming instant acceptance.
- Federal contracts often require native schedule files (Primavera P6 XER) alongside PDF reports, and expect the schedule to tie cleanly to cost/resource loading for progress payment purposes.
State and local New York agencies: agency-specific, not standardized
New York's state and local public agencies don't share a single standardized specification the way federal UFGS-pattern language does. Each agency writes its own general conditions and schedule requirements, shaped by its own mission:
- OGS � public building construction, often under CM-at-risk delivery, with schedule requirements set in that specific contract's general conditions.
- DASNY � financed construction for CUNY, SUNY, and institutional clients, where the review culture can reflect the client institution as much as DASNY itself.
- NYC DEP � water and wastewater infrastructure, with schedule requirements tied to utility shutdown coordination and regulatory review windows.
- MTA � capital transit construction, where schedule logic has to respect negotiated track-access and outage windows as a contractual constraint, not a planning assumption.
- Port Authority (PANYNJ) � aviation, port, and bridge/tunnel infrastructure performed inside operating, often security-restricted facilities.
Because these specifications aren't standardized across agencies the way federal specs are, the first scheduling task on any New York state or local contract is reading that specific agency's general conditions in full � assuming last year's similar-sounding project used the same rules is a common and avoidable mistake.
What doesn't change: the scheduler's first checklist
Regardless of whether a contract is federal or New York state/local, the same first-pass questions apply before a baseline gets built:
- What specific specification section governs the schedule, and what format (software, file type) does it require for submission?
- What is the required baseline submittal window after notice to proceed, and what is the formal review-and-acceptance cycle � including how many review rounds the specification allows before escalation?
- What coding structure (cost/pay item, WBS, agency-specific activity IDs) does the reviewer expect, so cost and schedule can be cross-referenced?
- What access, outage, or occupied-facility constraints does this specific contract impose, and are they built into the logic or only described in a narrative?
HADVEN applies this same first-pass discipline whether a project falls under federal and USACE specifications or one of New York's state and local agency frameworks described on the New York construction scheduling hub.